Emergency fiber relocation for Public Works Building
Troy
Summary
The Rochester Road utility project uncovered the city's fiber line on poles being replaced, and a bid waiver was approved to move it quickly. Without fast action, the DPW connection and the road project schedule would be delayed.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jul 13, 2026.
Impact analysis
$15,347.45, plus up to $12,000 in contingency funds if the underground conduit needs replacing.
City operations and residents who rely on DPW services stay connected and the Rochester Road project stays on schedule.